  Ten days to answer: how long a federal solicitation gives you
  https://offra.cc/blog/how-long-bidders-get-to-answer
  By The Offra team
  Published: 2026-10-28
  Language: en · Category: Public procurement
  © Consuly Pte. Ltd. — republished with attribution and a link to the canonical URL.
-->

Of the **17,082** federal solicitations first posted between 8 September and 16 October 2026, half
gave bidders **ten days or less** to answer. Only **8.6%** gave a month or more.

Most of that is one agency. Seven in ten of those solicitations (12,066) came from the Defense
Logistics Agency, and 96% of DLA's are titled with a supply class code and a part name:
`59--SWITCH,THERMOSTATIC`, `48--SEAT,VALVE`. They run on a fixed clock. Nine in ten DLA windows
fell between 7 and 14 days, and about one in a thousand was extended.

Take DLA out and the median is still ten days, but the spread opens up. Of the other **5,016**,
**28%** gave less than a week and **23%** gave a month or more. Which end you land on depends on
what kind of solicitation it is, who is buying, and whether the work is set aside.

These figures come from Offra's own catalogue of open notices. How they were counted, and what that
leaves out, is at the end.

## Two kinds of solicitation, two clocks

A federal buyer can post a solicitation in two ways. A **combined synopsis/solicitation** is a
commercial buy where the notice *is* the solicitation: one posting, quotes due. A standalone
**solicitation** usually follows a separate notice and carries a full package. Four in five
federal solicitations in the sample were the combined kind.

| | Solicitations | Median window | Under 7 days | 30 days or more |
|---|---|---|---|---|
| Combined synopsis/solicitation (excl. DLA) | 2,191 | **7 days** | 39% | 6% |
| Solicitation (excl. DLA) | 2,825 | **16 days** | 19% | 36% |
| DLA, both kinds | 12,066 | 10 days | 7% | 3% |

The rules explain most of the gap. Under the FAR's current text, rewritten in the overhaul and
adopted agency by agency, a commercial buy, and anything at or below the simplified acquisition
threshold, has **no minimum response time**. The standard is "a reasonable opportunity to respond".
A trade agreement can set a floor of 10 or 40 days, depending on whether the agency put the buy in
its annual forecast. Other non-commercial acquisitions get at least **30 days** from the
solicitation, and research and development gets 45 days from the presolicitation notice.

You can see that floor in the data. 17% of the standalone solicitations, outside DLA, gave
exactly 30 or 31 days.

## By sector and agency

Outside DLA, construction gives the most time and moves the most. Goods have the shortest median.

| Sector | Solicitations | Median window | Under 7 days | 30 days or more | Deadline moved |
|---|---|---|---|---|---|
| Construction | 485 | **16 days** | 13% | 31% | **22%** |
| Services | 1,510 | 10 days | 28% | 16% | 20% |
| Goods | 2,925 | 9 days | 31% | 26% | 10% |

"Deadline moved" counts only solicitations whose deadline had passed by 26 October, so a notice
that was still open could not miss a late extension.

By agency, the Navy is the outlier. Half its solicitations gave close to a month, and a quarter sit
at exactly 30 or 31 days. The Air Force and the Coast Guard sit at the other end: a median of one
week, with more than four in ten windows under seven days.

| Buyer (excl. DLA) | Solicitations | Median window | Under 7 days | 30 days or more |
|---|---|---|---|---|
| Navy | 1,460 | **29 days** | 17% | 49% |
| Army | 799 | 10 days | 27% | 15% |
| Air Force | 490 | **7 days** | 41% | 11% |
| Veterans Affairs | 474 | 10 days | 25% | 12% |
| Coast Guard | 189 | **7 days** | 46% | 9% |
| Forest Service | 173 | 10 days | 21% | 8% |
| Energy | 112 | 8 days | 19% | 11% |
| State | 102 | 14.5 days | 11% | 17% |

## Set-aside work runs on the shortest clock

Outside DLA, the **3,090** solicitations set aside for small business had a median window of
**7 days**, and 36% gave less than a week. The **1,926** open to everyone had a median of **22
days**, and 42% gave a month or more.

That is not a rule written against small firms. It follows from what is set aside: 57% of the
set-aside solicitations were combined synopsis/solicitations, against 23% of the open ones. Small
commercial buys are where the set-asides are, and small commercial buys carry no minimum.

The consequence is the same either way. A firm that bids mostly in the small-business lane is
bidding mostly against a one-week clock.

## Deadlines move, and nearly always later

Outside DLA, **14%** of closed solicitations had their deadline extended by a later amendment, by a
median of **4 days**. That rises to 22% in construction, 23% at Veterans Affairs and 24% at the Air
Force. A deadline brought *forward* is rare: 21 of 5,016.

An extension is good news only if you see it, and it often arrives as one line in an amendment
you also have to acknowledge. [The package moved after you read it](/blog/the-package-moved-after-you-read-it)
covers what else changes in that amendment.

## State and local boards give about twice as long

The state and local boards Offra covers gave a median of **22 days** across **5,693** notices posted
in the same six weeks. Only 9% gave less than a week.

| Board | Notices | Median window | Under 7 days | 30 days or more |
|---|---|---|---|---|
| City and agency boards on OpenGov | 2,151 | 23 days | 6% | 31% |
| Virginia eVA | 937 | 12 days | 26% | 16% |
| TxDOT lettings | 774 | 26 days | 0% | 1% |
| Texas ESBD | 707 | 25 days | 1% | 17% |
| Cal eProcure | 530 | 20 days | 1% | 27% |
| Los Angeles (RAMP) | 360 | 13 days | 24% | 11% |

TxDOT lets on a monthly calendar, so its window barely varies: the middle half of its lettings fell
between 23 and 26 days. On the OpenGov boards, 1,758 notices published a questions deadline, and it closed
a median of **9 days** before bids were due. That leaves roughly two weeks to read the package and
ask. New York City, San Francisco and the District each had fewer than a hundred notices in the
window, so they count in the total but are not shown on their own.

## Earlier warning, when there is any

Outside DLA, **449** of the 5,016 federal solicitations (9%) had a presolicitation or sources sought
notice under the same number first. It came a median of **17 days** before the solicitation, and
those buys gave a median of **47 days** from first notice to deadline. The solicitation alone gave
30. Treat 9% as a floor: an earlier notice archived before Offra's catalogue started cannot be
matched.

When an earlier notice exists, it is worth more than the solicitation's own window, which is the
case for [answering a sources sought notice](/blog/how-to-answer-a-sources-sought-notice) rather
than waiting for the solicitation.

## What this changes for a bidder

1. **Look every day, or be told every day.** If you check once a week, a seven-day window can open
   and close between two looks. A [free Offra account](/start) runs up to ten saved searches on a
   morning digest, so a matching solicitation comes to you instead of waiting for your next look.
2. **Keep the standing documents ready.** In the set-aside lane the median window is a week. That
   leaves no time to sort out a registration, a capability statement or past-performance write-ups
   after the notice arrives. [Registered in SAM is not one thing](/blog/registered-in-sam-is-not-one-thing)
   is a good place to start.
3. **In construction, do not plan backward from the first deadline.** One in five moved. Watch the
   notice, and expect the date in your schedule to change before the work does.
4. **If proposal capacity is your limit, state and local boards give it more room.** Twice the
   median window means each bid costs less rush.

## What this does not show

**Six weeks, one season.** The sample spans the end of the federal fiscal year, usually its
busiest buying month, and an October that opened on a
[continuing resolution](/blog/bidding-under-a-continuing-resolution). Windows in other months may
run differently.

**How a window is counted.** Calendar days, weekends included, from the posting date the buyer
stamps on the notice to the deadline's date in US Eastern time. SAM.gov publishes each amendment as
a new notice with its own posting date. So each federal solicitation is counted once, by
solicitation number and buyer, and runs from its first version's posting date to the deadline that
version carried. An extension is a later version with a later deadline. The state and local boards
amend in place, so their first deadline is the one Offra recorded before any change.

**What is missing.** A notice whose deadline is more than about six months out is not in the feed
until it comes within range. Offra's catalogue usually records a federal notice the day after it is
posted, so a notice that opens and closes within a day can slip past: 103 of the 17,082 had a
window of a day or less, and the shortest windows are, if anything, undercounted. Washington's WEBS
publishes no posting date and is left out. And orders placed under existing contracts are mostly never
posted publicly at all.

**What a sector is.** It comes from the notice's NAICS code. Goods are manufacturing, wholesale and
retail; services are the service sectors; construction is NAICS 23.

## Sources

- [SAM.gov contract opportunities](https://sam.gov/opportunities), through its public API, and
  the state and local boards named above, as recorded in Offra's catalogue from 19 August to
  26 October 2026. Queried 26 October 2026.