28 days left Washington
Pierce County
This project provides for the Electrical lighting controls replacement to include: replacing the existing lighting control panels with a new control system including new central lighting control station, provide wiring for integration of control system into local network across the six buildings at our Central Maintenance Facility.
21 days left Washington
City of Seattle
Project Description: Renovation of an existing Park's storage and restroom building which has received fire damage. Works include but not limited to renovating the restrooms to become two single occupancy restrooms, replacing fired damaged structural timber frames, adding shear walls, replacing existing roof, removing existing stone chimney, and replacing entire electrical system. Other accessibil
28 days left Washington
Pierce County
Orangegate Park is an approximately 150-acre property that is located in the Summit-Waller community at the intersection of 84th Street East and 46th Avenue East. Pierce County acquired the property from Washington Department of Natural Resources in 1998. The property is split by the Tacoma Water Pipeline and Pipeline Trail as well as 84 th Street East. The portion of Orangegate Park south of 84 t
21 days left Washington
City of Seattle
Project Description: Project includes pavement removal, roadway paving, sidewalks, curb ramps, driveways, storm drain, landscaping, striping and signage. Additvie includes electrical, foundations and pedestrian lighting. Engineer's Estimate: $2,800,000 - $3,300,000 Additive: $270,000 - $330,000 Project Location: East side of 1st Ave NE from N 120th St to N 130th St.
30 days left Washington
City of Seattle
Project Description: The City of Seattle seeks Statements of Qualifications (SOQs) from qualified firms to provide Design-Build (DB) Services for the Gorge Powerhouse Crane Replacement Design-Build Project (Project). The Project will consist of design, demolition, construction, and commissioning services for the replacement of two overhead bridge cranes, rated at 150T each. Engineer's Estimate: $
28 days left Washington
City of Seattle
Project Description: This Project consists of performing spot sewer rehabilitation to existing sewer and drainage pipes of varying depth and size, including Cured in Place Pipe rehabilitation. This includes coordinating with other utilities, surface removal, excavation, dewatering, bypass pumping, replacing pipe, pipe fittings, maintenance holes and channels, bedding, jet cleaning, CCTV inspection
28 days left Washington
City of Seattle
Project Description: The Roosevelt Way Preservation Project consists of planing the asphalt overlay and the removal and replacement of select areas of concrete panels and base repair. The project also includes the intersection realignment at NE 113th Street and the installation of curb bulbs at NE 114th Street and NE 115th Street. The work also includes the installation of ADA compliant curb ramps